In October 2014, Global Wind Service (GWS) completed the installation of 8 Siemens 2.3MW turbines for the Mid Hill wind farm extension 20 miles south of Aberdeen, Scotland.

  • The first turbine was successfully installed at 8:40 on the 1st September.
  • Installation rate of 1 turbine every 4 days thanks to a highly efficient project team and good weather.
  • GWS was responsible for the craning and installation, project management and health and safety on site.

GWS also installed Mid Hill 1 in May 2014, which consists of 25 Siemens 2.3MW turbines.