Global Wind Service (GWS) is very pleased to announce the successful completion of the installation contract on the Riffgat wind farm in the German Bight. The project, which consists of 30 Siemens 3.6 MW turbines, was completed in record breaking time (a total of 57 working days) and utilised a full spread of Fred. Olsen related companies including, GWS, Fred. Olsen Windcarrier AS and Fred. Olsen Windcarrier A/S.

The Bold Tern and Bayard 1 both performed excellently throughout the project and the GWS installation teams recorded no accidents throughout the project.

Bold Tern has subsequently demobilised and remobilised for her next project in UK waters.